| The breakwater will have to be constructed in sections in precast yards and towed to location, aligned and placed on seabed which will be strengthen by non-dredging method such as “stone column” or “deep cement grouting” to minimize impact on marine ecology. During the casting process, it is possible to “cast-in” special features inside and outside the breakwater structure, hence making it possible to tailor for innovative uses, adding new life and meaning to the otherwise inert structure. | 
 
									 
	
									 
									 
										 
																																																																																			 
															 
																																																																																																																																	 
									 
																																																																																																																																																															 
															 
																																																																																																																																																																																																				 
									 
																																													    																																																																						 
																					 
																																																																																																																																																																																																																																																																																																																 
									